Thanks, Jan. I use this:
project.BaseCalendars[1].Period(date1, date2).set_Working(false);
Dennis Huang
"Jan De Messemaeker" <ja*************@glo.be> wrote in message news:#8**************@TK2MSFTNGP11.phx.gbl...
Hello,
MSProject.application.activeproject.basecalendars( "Standard").period("25/12/03").working=false
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
"Wongalogic" <De*****@BlueVisions.com.au> schreef in bericht news:#P*************@TK2MSFTNGP11.phx.gbl...
Dear friends:
Do you know how to change working time in MS Project by C#? I want to create a MS project file from C# using Project Library 9.0. I got MSProject.Application and MSProject.Project objects. Now I want to use them to set non-working date/time, like set 25-Dec-03 as a non-working day. Do you know how to do it?
Thanks,
Dennis |